A company employs 15 persons working 44 hours a week . If 4 persons are ill, how many hours a week would the rest have to work to make up the time lost ?

60

55

50

None of these


Description (বিবরণ) :

প্রশ্ন: A company employs 15 persons working 44 hours a week . If 4 persons are ill, how many hours a week would the rest have to work to make up the time lost ?

ব্যাখ্যা: Remaining people = 15 - 4 = 11
15 people need to work for 44 hours.
So, 11 " " " " (44x15)/11" = 60 hours